Article 37
(Enforcement Rules)
The enforcement rules of this Act will be established by the central level responsible authority.
Article 38
(Guidance Plan)
The regulatory authority shall draft a guidance plan for the purposes of conserving soil and water resources and preventing or reducing the possibility of disasters, and shall report on the results of soil and water conservation within five years.
The guidance plan mentioned in the preceding paragraph will be made by the central level responsible authority and submitted to the Legislative Yuan for approval and the files.
Article 38-1
Any unfinished portion of soil and water conservation work may continue according to the soil and water conservation plan which was already approved in accordance with Slopeland Conservation and Utilization Act prior to the enforcement rules of the Act coming into force as of July 2, 1995; provided, however, that this Act shall still apply to any modification of the approved plan.
Article 38-2
Where this Act provides for soil and water conservation treatment and maintenance with respect to an act of development, operation or use which had been approved by the authority responsible for specific business and been implemented but not yet completed prior to the amendment to Slopeland Conservation and Utilization Act coming into force as of January 12, 1986, the soil and water conservation obligor must, within the time limit prescribed by the central competent authority in a public notice, draft a soil and water conservation plan and submit the same according to this Act to the regulatory authority for approval before implementing the plan. This Act as well as the relevant acts will apply where the soil and water conservation obligor fails to comply with the above within the prescribed time limit or to implement the plan in accordance with the applicable provisions of this Act.
The development, operation or use concerned may continue during the period in which the soil and water conservation plan mentioned in the preceding paragraph is being submitted and reviewed, provided soil and water conservation is properly treated and maintained and other relevant safety measures properly taken.
Article 39
(Date of Enforcement)