Chapter III Establishment and Inspection of Mobile Broadband Telecommunications Networks
Section 2 Inspection of mobile broadband dedicated telecommunications networks
Article 23
After completing the establishment of the base station and network, the applicant shall conduct the test in accordance with the following requirements before applying for inspection:
1. To register the start and end dates for the test implementation at least 5 days prior to conducting the test.
2. Each test shall last no longer than 5 days
The applicant shall attach the letter of approval for the network establishment plan, frequency use certificate, and the following documents to apply to the competent authority for inspection:
1. Base station items:
(1) The inspection application form.
(2) Self-assessment of the inspection items designated by the competent authority and the inspection record list.
(3) The base station equipment inspection detailed list.
2. Network items:
(1) The inspection application form.
(2) Self-assessment of the inspection items designated by the competent authority and the inspection record list.
Article 24
In the event that the administrator of a dedicated telecommunications network for experiments, research, and development adapts the telecommunications equipment in the same installation place for use as a mobile broadband dedicated telecommunications network and there is no change in the network establishment plan, an application attaching the documents below for exemption from the inspection may be applied. The competent authority shall issue a mobile broadband dedicated telecommunications network license if the application is approved:
1. Documents regarding approval of the establishment of the dedicated telecommunications network for experiments, research, and development.
2. Frequency use certificate and network inspection approval certificate.
3. Other documents designated by the competent authority.
An applicant may apply for exemption from inspection if they meet the following requirements. If the application is approved, the competent authority shall not issue the mobile broadband dedicated telecommunications network license; instead, the applicant is eligible to use the network during the valid period of the frequency use certificate:
1. The establishment period is no more than 30 days.
2. The total establishment period applied by the same applicant in the same year for the same domain is no more than 60 days.
Article 25
In principle, the competent authority shall conduct document inspection, but, if necessary, onsite inspection will be implemented.
When applying for inspection to the competent authority, the applicant shall provide the test equipment and necessary assistance required for the inspection.
For the onsite inspection, the competent authority shall notify the applicant of the scheduled inspection date, and the applicant shall cooperate with the competent authority to conduct the inspection in accordance with the inspection date.
Those that fail to pass the onsite inspection may request reinspection. The reinspection date shall be set in cooperation with the competent authority and the reinspection is limited to one time only.
In case of failure to pass the inspection, the competent authority shall reject the application.
Article 26
The competent authority will issue a mobile broadband dedicated telecommunications network license to those that pass the inspection.
The valid period of the mobile broadband dedicated telecommunications network license shall not exceed the effective date of the frequency use certificate.
In case of loss or damage of the mobile broadband dedicated telecommunication network license, the applicant shall give an account of the reasons and apply to the competent authority for reissuance. If there is any change in the items stated in the license, the applicant shall apply to the competent authority for renewal.
In case of reissuance or revision of the mobile broadband dedicated telecommunications network license in accordance with the preceding requirements, the valid period of the reissued or renewed license shall be same as that of the original license.
After the expiration of the mobile broadband dedicated telecommunications network license, if the installer still needs to continue to use the mobile broadband dedicated telecommunications network, they shall attach the renewal application form and apply to the competent authority to renew the mobile broadband dedicated telecommunications network license within 2 months from the day that is 3 months before the expiration of the license.
Unless otherwise provided by laws and regulations, the mobile broadband dedicated telecommunications network license shall not be leased, lent, transferred, or pledged to others.