Article 5
Stations are classified according to bogus antenna and installed-on-site antenna.
When applying for installed-on-site stations, the school should apply for written consent from the administrative authority of education, and apply to the authority for establishment permit and frequency allocation with the above-mentioned written consent.
Article 6
After receipt of establishment permit and frequency allocation, applicant should prepare the following documents and apply to the authority for a Station Establishment Permit issued by the authority:
1. Copy of approval letter issued by the authority.
2. Application Form for Station Establishment Permit .
3. Station facility specification stating clearly the equipment origin factory, model, catalogue together with the system diagram such as: wireless facilities should have clear statements of electric power, station frequency, transmission method, and include information such as the antenna gain, coordinate, antenna field pattern, etc.
4. Curriculum Vitae of engineering supervisor .
5. When the antenna pylon is built upon rooftop of a building, an original copy of building structure safety evidence examined and issued by construction or structure engineer.
The examination period for the above mentioned application is three months.
Article 7
Height of the antenna pylon installed should not violate the aviation safety standards and should abide by the regulation of prohibited construction nearby airports, aviation aid facilities.
Antenna Pylon should be equipped with signs and obstacle signal lights conforming to the regulations of aviation obstacle signs and signal lights facilities.
Article 8
The Station Establishment Permit is valid for one year. When necessary the applicant may apply for an extension period of no more than 6 months to the authority 30 days before the expiration date stating clearly the reason for extension and submit the original establishment permit with the application.
Station Establishment Permit should have records on the following information:
1. Name of station
2. Location of installation
3. Transmitter brand, model, quantity and quantity of electric power amplifier
4. Range of station frequency
5. Bandwidth frequency of station
6. Electric power
7. Station call sign
Article 9
Applicants using bogus antennas after obtaining the Station Establishment Permit, installing the facilities and qualified the examination of the authority can apply for a Station License issued by the authority. Applicants using antenna facilities should self-test the inner system processing of the station, electric wave coverage and interference appraisal. Applicant should apply for an examination of qualification to the authority after testing. Qualifiers of the examinations holding the Station Establishment Permit may apply for a Station License issued by the authority.
The processing period for the above mentioned application is three months.
When carrying out test on the first item, tester can only transmit test sound, estimate measure of radiation to test strength of electric field, appraise electric wave coverage range and jamming conditions.
Station should not interfere with other stations’ broadcasting when carrying out tests.
Stations applying for inspection should submit the following documents:
1. Transmitter’s original proof of factory production. Imported models should include Import Certificate (proof documents should at least include brand name, model, serial number, date of production)
2. Self-tested record of Transmitter.
3. Map of electric wave coverage
4. Antenna pylons abiding by Construction regulations should apply for sundries license. A copy of the sundries of license.
Article 10
Station License is valid for three years. When expires, applicants may self-test and submit a self-tested record of transmitter together with application to the authority for a new license issued by the authority 30 days before the expiry date.
Station License should specify the following information:
1. Name of Station
2. Name of School
3. Person in Charge of the School
4. Person in Charge of the Station
5. Engineering Supervisor
6. Approved Electric Power
7. Frequency of Station
8. Bandwidth of Station
9. Station Call Sign
10. Location of installation
11. Brand name, model, serial number of main and sub transmitter, electric power and quantity of power amplifiers.
12. Location of Studio
Station transmitter should have license for each separate facility but main and sub transmitters can be recorded on one license.
Article 11
The station relocating or changing frequency, electric power, or transmitters should apply for a establishment permit from the authority and can only be put to use after qualifying the inspection and obtaining a station license.
When applying for the establishment permit mentioned above should submit document stated in Paragraph 1 of Article 6 and follow the process stated in. As to simple replacement of worn out facilities or change of frequency and electric power, documents mention in No.4 and 5 of Paragraph 1 of Article 6 can be exempted.
Application for examination as mentioned in Paragraph 1 should submit documents stated in Paragraph 5, Article 9. As to simple replacement of facilities or change of frequency and electric power, documents mention in No.3 and No.4 of Paragraph 5 of Article 9 can be exempted.
Article 12
When Station Establishment Permit or Station License are lost or ineligible for use due to severe damage, an announcement should be immediately put up on newspapers proclaiming invalidity and report to the authority to re-issue a new permit or license.
Article 13
When information recorded on the Station Establishment Permit or the Station license has been altered, a report should be made to the authority to re-issue a new permit or license.
Article 14
Re-issued Station Establishment Permits and Station Licenses based on the two Articles mentioned above have the same validity and expiration period as the original permits and licenses.
Article 15
The Station Establishment License and Station License is non-transferable nor can be rented or given to a third party.