Goto Main Content
:::

Chapter Law Content

Chapter 6 Counselling on correction and consultation
Article 16
If the building owners fail to complete correction within two years from the dates of public announcements of the unjustifiable uses of factories and relevant buildings or upon expirations of the reduced or extended time limits as approved by the Park Bureaus, the Park Bureaus may, pursuant to Paragraph 4 of Article 20 of the Act, fine the building owners with an amount of up to 10 percent of the present government accessed land value of the park land where the buildings are located and notify the building owners to propose correction plans within one month in order to facilitate the process and completion of consultations.
The correction plans under the preceding paragraph shall contain the following matters:
1. Causes of determination of unjustifiable uses, execution status, and reasons for failure to complete the correction within two years.
2. Concrete scheme of correction, explanation of funds, and times required for completion of correction.
3. The concrete effect after completion of correction, and the reason of non-existence of unjustifiable uses.
4. Other necessary matters.
Article 17
After receipt of correction plans, the Park Bureaus shall convene meetings of the review teams for the review thereof, and may notify the building owners to give explanations at the meetings.
Article 18
After the correction plans submitted by the building owners have been adopted and approved by the resolutions at the meetings of review teams, the Park Bureaus may enter into the records of completion of consultation with the building owners in respect of the approved correction plans.
The record of completion of consultation under the preceding paragraph may be made in administrative contract, agreement, affidavit or other forms.
Starting from the day following date of the consultation record, the building owners shall complete the correction according to the contents and time limit of the approved correction plans, and shall, on monthly basis, prepare the execution progress tables and send such tables to the Park Bureaus for recordation.
Article 19
For the building owners who have completed the consultation with the Park Bureaus, the Park Bureaus may provide counseling from time to time, and may irregularly dispatch personnel for the patrol and inspection thereof; and, if necessary, may convene the audit meetings.
Article 20
Building owners who fail to complete the correction according to contents and time limits of the approved correction plans, unless otherwise agreed in the records of completion of consultation under Paragraph 1 of Article 18, shall be deemed as failure to complete consultation with the Park Bureaus at due time.
Article 21
Building owners who complete the correction according to the approved correction plans shall follow the requirements of Article 15.